Work Plan¶
The following is a tentative one-year project schedule oriented to the delivery of interim results and management check-points. This serves as a guide only, to be updated as determined by participants.
Statement of Work and Schedule
- Month 1:
- Use the present one-year Working Group plan to elaborate particular objectives for various team members and relationships with stakeholders.
- Create an effective participatory R&D collaborative trajectory involving participants from multiple organizations.
- Identify and express in XalgoRuleSchema (XRS) a small number of scenarios in order to test understanding and utility.
- Design structured test protocols to compare data input/output relative to results from at least three widely deployed production-class systems currently in use.
- Adapt or create a simple online test service for validating automated rule fulfillment:
- Multilingual, accessible (WCAG 2.0) end-user interface.
- Rapid iterative diagnosis and documentation of discrepancies.
- Link to comprehensive issues management workflow.
- Months 2-3-4:
- Test oughtomation scenaros with the available reference implementations.
- Incrementally increase rule complexity; refining the process for accuracy and for speed.
- Complete and field-test the online service for validating automated rule fulfillment.
- Jointly develop and present a first interim report to stakeholders.
- Develop a draft concept-of-operations for risk management
- Months 5-6-7:
- Incrementally broaden collaborative work on rule expression and validation.
- Roll out and support version 1.0 of the online service.
- Publish version 1.0 documentation (technical, financial, legal).
- Broaden consultations (technical, financial, legal).
- Create hypothetical management/financial models for proliferation.
- Jointly develop and present a second interim report to stakeholders.
- Months 8-9-10:
- Increase collaborative work on rule expression and validation.
- Test and debug complicated rules, exceptions, anomalies and dependency chains (forward-chained, backward-chained rules).
- Commence scheduled version 1.x updates each quarter (3 months).
- Refine and publish documentation (technical, financial, legal).
- Jointly develop and present a third interim report to stakeholders.
- Month 12
- Develop and present a proposed workplan for the next two years.
- Contract out an arms-length study for stakeholder/community views.
- Assess demand for training, and make arrangements accordingly.
- Assess demand for support, and make arrangements accordingly.
Updated by Craig Atkinson about 2 years ago · 4 revisions