# Work Plan
2
3
Following is a tentative one-year project schedule oriented to the delivery of interim results and management check-points. This serves as a guide only, to be updated as determined by participants.
4
5
- Month 1: 
6
   - Use the present one-year Working Group plan to elaborate particular objectives for various team members and relationships with stakeholders.
7
   - Create an effective participatory R&D collaborative trajectory involving participants from multiple organizations.
8
   - Identify and express in XalgoRuleSchema (XRS) a small number of scenarios in order to test understanding and utility.
9
   - Design structured test protocols to compare data input/output relative to results from at least three widely deployed production-class systems currently in use.
10
   - Adapt or create a simple online test service for validating automated rule fulfillment:
11
      - Multilingual, accessible (WCAG 2.0) end-user interface.
12
      - Rapid iterative diagnosis and documentation of discrepancies.
13
      - Link to comprehensive issues management workflow.
14
- Months 2-3-4: 
15
   - Test oughtomation scenaros with the available reference implementations.
16
   - Incrementally increase rule complexity; refining the process for accuracy and for speed.
17
   - Complete and field-test the online service for validating automated rule fulfillment.
18
   - Jointly develop and present a first interim report to stakeholders.
19
   - Develop a draft concept-of-operations for risk management
20
- Months 5-6-7:
21
   - Incrementally broaden collaborative work on rule expression and validation.
22
   - Roll out and support version 1.0 of the online service.
23
   - Publish version 1.0 documentation (technical, financial, legal).
24
   - Broaden consultations (technical, financial, legal).
25
   - Create hypothetical management/financial models for proliferation.
26
   - Jointly develop and present a second interim report to stakeholders.
27
- Months 8-9-10:
28
   - Increase collaborative work on rule expression and validation.
29
   - Test and debug complicated rules, exceptions, anomalies and dependency chains (forward-chained, backward-chained rules).
30
   - Commence scheduled version 1.x updates each quarter (3 months).
31
   - Refine and publish documentation (technical, financial, legal).
32
   - Jointly develop and present a third interim report to stakeholders.
33
- Month 12
34
   - Develop and present a proposed workplan for the next two  years.
35
   - Contract out an arms-length study for stakeholder/community views. 
36
   - Assess demand for training, and make arrangements accordingly.
37
   - Assess demand for support, and make arrangements accordingly.